News by Date
News by Category
Solar System
Stars
White Dwarfs
Supernovas
Neutron Stars
Black Holes
Milky Way Galaxy
Normal Galaxies
Quasars
Galaxy Clusters
Cosmology/Deep Field
Miscellaneous
Press Resources
Status Reports
Press Advisories
Image Releases
Release Guidelines
Image Use Policy
NASA TV
Biographies/Interviews
Web Shortcuts
Chandra Blog
RSS Feed
Chronicle
Email Newsletter
News & Noteworthy
Image Use Policy
Questions & Answers
Glossary of Terms
Download Guide
Get Adobe Reader
Chandra @ NASA
Visit the Chandra pages at the NASA portal (opens in new window)
Image Use
Image Use Policy & Request Form
Guidelines for utilizing images, applets, movies, and animations featured in this Web Site.
Getting Hard Copies of Images
Ways to obtain photos, slides, etc of Chandra images.
Operations CXO Status Report

Friday 3 February 2017 9.00am EST

During the last week the observing schedule was replanned to remove the grating from the observation of 4U 1630-47.

A real-time procedure was executed on Feb 1 to swap the prime solid-state recorder (SSR) from the B-side to the A-side. This swap concludes a six-month interval of health and trending data collection on SSR-B. A second real-time procedure was executed on Feb 1 to perform a routine self-check of the Electrical Interface Assembly (EIA) Sequencer.

The schedule of targets for the next week is shown below and includes GRS 1716-249, which was accepted as a Director's Discretionary Time Target of Opportunity on Jan 31, and iPTF17cw, which was accepted as a Director's Discretionary Time Target of Opportunity on Jan 23.



------------------------------------------
Radiation Belts Feb 6 GRS1716-249 ACIS-S/HETG NGC4206 ACIS-S LEDA87445 ACIS-I NGC3600 ACIS-S Feb 7 IRAS17020+4544 HRC-S /LETG NGC4220 ACIS-S IRAS17020+4544 HRC-S /LETG Feb 8 iPTF17cw ACIS-S Radiation Belts Feb 9 Abell586 ACIS-I NGC3583 ACIS-S IRAS17020+4544 HRC-S /LETG NGC4411b ACIS-S LEDA87445 ACIS-I Feb 10 spog5260 ACIS-S IRAS17020+4544 HRC-S /LETG Abell586 ACIS-I Radiation Belts Feb 11 Abell586 ACIS-I NGC4237 ACIS-S Feb 12 CygnusA-Nucleus ACIS-I

------------------------------------------

All spacecraft subsystems continued to support nominal operations.