Friday 8 December 2000 7.30am EST
During the last week, Chandra completed the observing schedule as planned.
Real-time procedures were completed during the week to insert the LETG for a series of planned observations on Dec 5, and to retract the LETG on Dec 7. Both grating motions were nominal. In addition, a check of the CPE warm start count was made on dec 5 that showed the value remained at 1. The planned observations for the coming week are as follows: |
------------------------------------------
CDFS ACIS-I Dec 10
AXAF Southern Deep Field ACIS-I Dec 11
Radiation Belts
AR Lac (multiple) HRC-I Dec 12
M31 Nucleus/Trans ACIS-I
CDFS ACIS-I
HR1099 (multiple) HRC-I Dec 14
Radiation Belts
PMN J1131+0455 ACIS-S Dec 15
E0102-72 (multiple) ACIS-I
AXAF Southern Deep Field ACIS-I Dec 16
------------------------------------------
All spacecraft subsystems continued to operate nominally.
Return to Status Reports