News by Date
News by Category
Solar System
Stars
White Dwarfs
Supernovas
Neutron Stars
Black Holes
Milky Way Galaxy
Normal Galaxies
Quasars
Galaxy Clusters
Cosmology/Deep Field
Miscellaneous
Press Resources
Status Reports
Press Advisories
Image Releases
Release Guidelines
Image Use Policy
NASA TV
Biographies/Interviews
Web Shortcuts
Chandra Blog
RSS Feed
Chandra Mobile
Chronicle
Email Newsletter
News & Noteworthy
Image Use Policy
Questions & Answers
Glossary of Terms
Download Guide
Get Adobe Reader
Chandra @ NASA
Visit the Chandra pages at the NASA portal
Image Use
Image Use Policy & Request Form
Guidelines for utilizing images, applets, movies, and animations featured in this Web Site.
Getting Hard Copies of Images
Ways to obtain photos, slides, etc of Chandra images.
Operations CXO Status Report

Thursday 5 August 1999 7.00am EST

The following is an overview of the events that occurred over the last 24 hours. Completed a successful 5 minute IPS #4 burn using Liquid Apogee Engines (LAE) #2 and #4. The new perigee is now 5,657 km, the apogee is 139,141 km and the orbital period is 61 hours 7.3 minutes. IPS #5 burn is scheduled for Saturday, August 7 at 1:43 AM and will be an approximately 8 minute burn also using LAE #2 & #4.

Measured optical cavity pressure of 8.57 E-06 Torr. Pressure has been reduced from 8.8 E-06 in the last 24 hours

Performed ACIS internal calibrations.

Performed Dark Current Calibrations on the Aspect Camera Assembly.

Events scheduled for the next 24 hours

  • Continue ACIS calibrations.
  • Develop updated Chandra orbit parameters and targeting plans for IPS #5
  • Perform Earth Scan 20 in preparation for IPS #5.