News by Date
News by Category
Solar System
Stars
White Dwarfs
Supernovas
Neutron Stars
Black Holes
Milky Way Galaxy
Normal Galaxies
Quasars
Galaxy Clusters
Cosmology/Deep Field
Miscellaneous
Press Resources
Status Reports
Press Advisories
Image Releases
Release Guidelines
Image Use Policy
NASA TV
Biographies/Interviews
Web Shortcuts
Chandra Blog
RSS Feed
Chronicle
Email Newsletter
News & Noteworthy
Image Use Policy
Questions & Answers
Glossary of Terms
Download Guide
Get Adobe Reader
Chandra @ NASA
Visit the Chandra pages at the NASA portal
Image Use
Image Use Policy & Request Form
Guidelines for utilizing images, applets, movies, and animations featured in this Web Site.
Getting Hard Copies of Images
Ways to obtain photos, slides, etc of Chandra images.
Operations CXO Status Report

Friday 1 September 2006 9.00am EDT

During the last week the observing schedule was replanned to include an observation of SGR 1806-20 that was accepted as fast turn-around Target Of Opportunity (TOO) on August 30. Loads were replanned and uplinked on August 31. An observation of B2224+65 was impacted by the TOO and will be rescheduled in a later load.

The schedule of targets for next week is shown below and includes an observation of XTE J1810-197 coordinated with ground-based observations.

------------------------------------------
Radiation Belts Sep 3 RS Oph HRC-S/LETG Sep 4 M33 Field 2 ACIS-I SDSS J0750+4252 ACIS-S Sep 5 WR20a ACIS-I SDSS J0803+3022 ACIS-S Sep 6 Radiation Belts RS Oph HRC-S/LETG M33 Field 2 ACIS-I Sep 7 RXC J1147.3+5544 ACIS-S 1RXS J140654.5+525 ACIS-S Sep 8 RS Oph HRC-S/LETG Radiation Belts P14 ACIS-I Sep 9 P4 ACIS-I P3 ACIS-I P2 ACIS-I NGC 4194 ACIS-S NGC 5474 ACIS-S Sep 10 XMMU J2235.3-2557 ACIS-S XTE J1810-197 ACIS-S

------------------------------------------

All spacecraft subsystems continued to support nominal operations.