During the last 48 hours, Chandra completed observations of
Capella, and Cygnus X-2, the observatory passed through the
radiation belts with associated ACIS CTI measurements, and a
calibration observation of HZ-43 was started.
Real-time commanding was completed as planned at 1am on 11/10
to remove the ACIS engineering patch used to investigate a fix
for the FEP-0 parity error problem. The patch was installed for
approximately 24 hours and an initial look at the data suggests
that the problem did not reoccur during the test period. A
further test is expected.
During the next 24 hours, calibration observations will
continue of HZ-43 and the Coma cluster with HRC-S/LETG and
HRC-I and, and GTO observation of the Hubble Deep Field will be
conducted with ACIS-I.
Plans were finalized for the Leonids meteor show transition on
11/17, and incorporated into the next mission plan starting 8am
11/14.
The spacecraft subsystems continued to operate nominally.
|