| Activity |
Schedule |
Completion Status
|
| Mirror Grinding & Polishing | Dec 91 - Jul 95 |
 |
| Mirror Assembly | Jul 95 - Nov 96 |
 |
| Science Instrument Development | Jan 90 - Jan 97 |
 |
| Integral Propulsion System | Dec 93 - Mar 97 |
 |
| Spacecraft Structure Fabrication | Dec 95 - Mar 97 |
 |
| Mirror & Instrument Calibration | Nov 96 - Apr 97 |
 |
| Spacecraft Assembly & Testing | Apr 97 - Oct 97 |
 |
| Telescope Assembly & Testing | Apr 97 - Sep 97 |
 |
| Observatory Assembly & Testing | Oct 97 - Jun 99 |
 |
| Chandra arrive at KSC | Feb 4, 1999 |
 |
| Launch Preparation at KSC | Feb 1999 - July 17, 1999
|
 |
| Chandra/IUS transfer to Columbia |
Jun 99 |  |
| Launch!! | July 23, 1999 |
 |
| On orbit Calibration | TBD |
 |
| Scientific Operations | TBD |
 |